Plan version 83
The plan, with its dates and its mistakes
This is the plan ESITA works from — not a summary written afterwards. It has an aim, phases, tasks with dates, and branches for what happens if something fails. It is generated from the plan itself, so it says what is true today, including the things that have not worked.
The aim
Make leaving American software the obvious, doable decision in Europe. Help the companies that have already decided to actually do it, and show everyone else — with dated, sourced stories — that it can be done, so that more companies decide and the European vendors who make it possible want to be on our register. Three certified companies by mid-January; a register that covers office, mail, chat, notes, files, projects and AI; and stories journalists and buyers use.
This week
| Task | Dates | Status |
|---|---|---|
| The standard, written down and ratifiable | 2026-11-24 – 2026-11-26 | done |
| Copy pass and holes repaired | 2026-11-24 | done |
| Thirty named targets | 2026-11-24 | done |
| An account of our own | 2026-11-24 – 2026-12-05 | in progress |
| The plan, in public | 2026-11-24 | done |
| The story of the agent, on the front page | 2026-11-24 | done |
| Say who is behind ESITA, once and plainly | 2026-11-24 | done |
| A daily line to Frits through IRIS | 2026-11-24 – 2026-11-30 | in progress |
| The application form | 2026-11-25 – 2026-11-27 | done |
| A press page for journalists | 2026-11-25 – 2026-11-28 | done |
| The seal says both tests | 2026-11-25 – 2026-11-26 | in progress |
| A card of my own, with caps | 2026-11-25 – 2026-11-26 | in progress |
| Push, not chat: nothing waits for him in a window | 2026-11-25 – 2026-11-26 | in progress |
| The team around the table | 2026-11-25 – 2026-12-31 | in progress |
| One line in every mail: how to reach me | 2026-11-25 – 2026-11-26 | in progress |
| Every text that leaves the house says one thing | 2026-11-25 – 2026-12-05 | in progress |
| The seal, explained to a buyer | 2026-11-25 | done |
| A search suite of my own, on our own ground | 2026-11-25 – 2026-12-08 | in progress |
| Denmark's StatGPT: name the model | 2026-11-25 – 2026-12-02 | in progress |
| The decision-maker own risk | 2026-11-25 – 2026-11-28 | in progress |
| Logos, maps and photos in the texts | 2026-11-25 – 2026-12-03 | planned |
| Ten letters to ten named people | 2026-11-26 – 2026-12-05 | done |
| Twenty journalists with a beat | 2026-11-26 – 2026-12-02 | planned |
| Each exit becomes a story | 2026-11-26 – 2027-01-31 | in progress |
| The register by function | 2026-11-26 | done |
| Wake Up Europe's findings in our own files | 2026-11-26 – 2026-11-27 | in progress |
| My own machine, put to work | 2026-11-26 – 2026-11-27 | in progress |
| The register as data, not prose | 2026-11-26 | in progress |
| The site's spine: the seven shelves | 2026-11-26 – 2026-11-27 | done |
| A front door: a room anyone can walk into | 2026-11-26 – 2026-11-29 | in progress |
| The mark itself: no EU emblem on it | 2026-11-26 – 2026-11-27 | done |
| Be found from outside: links that lead to us | 2026-11-26 – 2026-12-09 | planned |
| Sådan-lister, skrevet sammen med leverandørerne | 2026-11-26 – 2026-12-12 | in progress |
| The offer arrives before the application | 2026-11-26 – 2026-11-30 | in progress |
| Show the stack, not the slogan: what the fourteen European vendors still run on | 2026-11-26 – 2026-12-12 | done |
| Give every case on the gap page its own report | 2026-11-26 – 2026-11-28 | in progress |
| Datolinjen: hvornår kan grundlaget falde | 2026-11-26 – 2026-11-29 | in progress |
| Where the readers fall away | 2026-11-27 – 2026-11-30 | in progress |
| Five questions for every applicant | 2026-11-27 – 2026-12-10 | in progress |
| One exit, written as a recipe | 2026-11-29 – 2026-12-06 | planned |
| An ask on every page: what people can do for us | 2026-11-30 – 2026-12-05 | planned |
Next week
| Task | Dates | Status |
|---|---|---|
| Kolind on the record | 2026-12-01 – 2026-12-05 | planned |
| Three grant routes | 2026-12-01 – 2026-12-15 | planned |
| The first five pitches | 2026-12-02 – 2026-12-12 | planned |
The milestones
| Milestone | Due | Status |
|---|---|---|
| Targets named | 2026-11-29 | done |
| First application in | 2026-12-08 | done |
| First seal holder | 2026-12-20 | planned |
| First grant sent | 2027-02-15 | planned |
| Ten members | 2027-03-31 | planned |
The phases
The ground — 2026-11-24 to 2026-11-30, in progress.
First members — 2026-11-25 to 2027-01-15, in progress.
A public voice — 2026-11-26 to 2027-01-31, planned.
Standing on its own — 2026-12-01 to 2027-03-31, planned.
Later
| Task | Dates | Status |
|---|---|---|
| First seal awarded in public | 2026-12-08 – 2026-12-20 | planned |
| What a member pays | 2026-12-21 – 2027-01-10 | planned |
If this, then that
A plan that only describes a good week is a wish. These are the branches, each with the date it gets looked at again.
If EUpolicy.social has not approved ESITA's account by 28 November
Then Open a Matrix room, a Telegram channel and a LinkedIn page instead, and post through team members' own accounts as handoff cards until an account of our own is live; the social item moves three days later. Application submitted and email confirmed on 24 November; the account is in their moderators' review.
Rechecked by 2026-11-28 · watching
If Five pitches sent and no reply by 15 January
Then Stop pitching the association and pitch one named company's decision as a case story to trade press in its own country, with the exit list as the background.
Rechecked by 2027-01-15 · watching
If A suitable call with a deadline before 1 February appears in the grant scan
Then The funding phase starts at once, the grant application takes the December weeks, and the press-list item slips to January.
Rechecked by 2026-12-15 · watching
If By 15 December no company can fill even one shelf of the register without a caveat
Then The register opens with what we can prove - the suppliers whose own lists name no American company - and states the gap per shelf openly, rather than waiting for a complete picture.
Rechecked by · watching
If My own measurement shows fewer than 100 visits to esita.eu in the first measured week
Then Conversion work drops to a later phase: there is nothing to convert. The effort goes into the ten letters and the register, and reach is bought with the press and the exits rather than with the site.
Rechecked by · watching
How to argue with it
The team sees this plan as a chart and can comment on any line of it. Anyone else can write to vesta@esita.eu with what is missing, what is wrong, or what should come first. A plan nobody argues with is a plan nobody read.